Power Plant & Electrical Substation Area of Expertise Cairo West 1x650 MW. Super-Critical Power Plant. Project: Cairo West Substation (500/220) KV.Location: Cairo.Start Date: 06/10/2018.Finish Date: 04/10/2020.Owner: CPEC.Client: (Hyundai Elec-POSCO Daewoo-KIC) Consortium.Consultant : PGESCO. South Of Helwan 3x650 MW. Super-Critical Power Plant. Project: South Of Helwan Substation (500) KV.Location: Beni Suif.Start Date: 22/11/2015.Finish Date: 30/01/2017.Owner: UEEPC.Client: ALSTOM Grid.Consultant : PGESCO. Suez Thermal 1x650 MW. Super-Critical Power Plant. Project: South Of Helwan Substation (500) KV.Location: Beni Suif.Start Date: 22/11/2015.Finish Date: 30/01/2017.Owner: UEEPC.Client: ALSTOM Grid.Consultant : PGESCO. Suez 3x 167MVA,500/220/11kV AIS S.S Extension. Project: Extension of Suez 3x 167MVA, 500/220/11kV AIS Electrical Substation.Location: Suez.Start Date: 01/10/2022.Finish Date: 15/12/2023.Owner: EETC.Client: Siemens Energy.Consultant : EETC. Beni Suif Industrial Substation (66/22) KV. Project: Beni Suef Industrial Substation (66/22) KV. ( 2 x 40 ) MVALocation: Beni Suif.Start Date: 09/09/2021.Finish Date: 19/01/2023.Owner: EETC.Client: Energya Steel Industry.Consultant : EETC. Ezz-Steel Substation (220/30) KV. Project: Ezz-Steel Substation (220/30) KV. Location: Ain sokhna-Suez.Start Date: 10/08/2021.Finish Date: 27/11/2022.Owner: Ezz Steel Factory.Client: Siemens Energy.Consultant : Shaker. Bshayer El-Kheir (3,5) Substation (66/11) KV. Project: Bshayer El-Kheir (3,5) Substation (66/11) KV. Location: Alexandria.Start Date: 50/08/2020.Finish Date: 01/09/2021.Owner: EETC.Client: Siemens Energy.Consultant : EETC. Samanoud Substation (66/11) KV. Project: Samanoud Substation (66/11) KV.Location: AL-Gharbya.Start Date: 07/03/2019.Finish Date: 20/02/2020.Owner: EETC.Client: EGEMAC.Consultant : EETC. Awlad Sakr Substation (66/11) KV. Project: Awlad Sakr Substation (66/11) KV.Location: AL-Sharqya.Start Date: 01/09/2017.Finish Date: 09/12/2020.Owner: EETC.Client: EGEMAC.Consultant : EETC. Samasta Substation (66/11) KV. Project: Samasta Substation (66/11) KV.Location: Beni Suif.Start Date: 01/03/2013.Finish Date: 05/01/2014.Owner: EETC.Client: Siemens Technology.Consultant : EETC. New Moot Substation (66/11) KV. Project: New Moot Substation (66/11) KV.Location: The New Valley.Start Date: 08/05/2012.Finish Date: 23/09/2013.Owner: EETC.Client: A.B.B.Consultant : EETC. Asiut Substation (66/11) KV. Project: Asiut Substation (66/11) KV.Location: Asiut.Start Date: 01/09/2011.Finish Date: 12/01/2013.Owner: EETC.Client: A.B.B.Consultant : EETC. Kom Abu Radi (66/22) KV. Project: Kom Abu Radi (66/22) KV.Location: Beni Suif.Start Date: 01/06/2011.Finish Date: 22/04/2013.Owner: EETC.Client: EGEMAC.Consultant : EETC. Kom Ahmer (66/11) KV. Project: Kom Ahmer (66/11) KV.Location: Beni Suif.Start Date: 01/12/2011.Finish Date: 05/10/2013.Owner: EETC.Client: EGEMAC.Consultant : EETC.